During a pole cut out test, what is the initial procedure for the climber?

Get ready for the Outside Lineman Year 1 Test. Focus with flashcards and multiple choice questions, complete with hints and explanations. Prepare thoroughly for your upcoming exam!

The initial procedure for the climber during a pole cut-out test involves placing the climber on the leg and holding the sleeve. This step is critical for establishing a secure and stable position on the pole before any other actions are taken. By ensuring that the climber is properly placed on the leg, it creates a secure footing which is vital for maintaining balance and safety as the test progresses.

It's important for the climber to be positioned correctly to minimize the risk of slipping or falling, which can happen if they are not securely placed. This foundational procedure sets the stage for safely performing the other tasks associated with the pole cut-out test.

In the context of safety practices, while ensuring that the safety harness is secure is crucial, doing so after correctly positioning the climber optimally supports their overall safety and effectiveness in the task. Climbing to the top and pushing gaff into the pole are subsequent actions that come after confirming a secure position and are not the immediate initial procedures for a climber during this test.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy